Bayhead Creek Culvert Repair Project on Killebrew Lake Rd

Share Bayhead Creek Culvert Repair Project on Killebrew Lake Rd on Facebook Share Bayhead Creek Culvert Repair Project on Killebrew Lake Rd on Twitter Share Bayhead Creek Culvert Repair Project on Killebrew Lake Rd on Linkedin Email Bayhead Creek Culvert Repair Project on Killebrew Lake Rd link

Project Brief

San Juan County is required by state law to replace a culvert located on Orcas Island under Killebrew Lake Road, just east of Laporte Road, with a fish-passable design. Funding for this project comes from FEMA and expires in early 2026. Replacement will occur in summer 2025.


Background

A storm in February of 2020 overwhelmed the culvert on Bayhead Creek under Killebrew Lake Road, just east of Laporte Road, and blew it out, causing catastrophic damage to the road and making it impassable. Following consultation from the Washington State Department of Fish and Wildlife (WDFW), San Juan County Public Works had the road reopened within 9 days after replacing the culvert with a temporary, 24-inch culvert under the condition the County would design a more permanent, fish-passable culvert. Now, with FEMA funding secured and a design in hand, the County is advancing plans to satisfy state requirements and install a 12-foot-wide box culvert specially designed to improve fish passage in Bayhead Creek and withstand future storms.


Construction Design

The County is considering several key factors in the construction design of this project, including cost, environmental impact, and how construction will affect the community. As such, two alternatives have been proposed - one that gets the job done as quickly and efficiently as possible but requires a maximum 9-day road closure, and a second that includes a single-lane bypass road for an estimated 3-4 weeks. These two designs are currently undergoing a constructability review with KBA, a construction management firm, to determine how each option will affect these variables. The County's goal is to minimize both inconvenience to the community and impact to the environment while staying within funding constraints.


Construction Window

This type of project typically requires dry weather to be completed efficiently. At the same time, the County wants to be mindful that the driest months of the year, July and August, are also our busiest in terms of traffic. As such, the County has identified two shoulder-season windows for starting construction: between Memorial Day Weekend and Fourth of July (if road closure option is chosen, road closure must be completed before Fourth of July), or after Labor Day Weekend. Physical construction will be completed within 45 days of the construction start date.


Next Steps & Timeline

After completion of the constructability review, the County will work with the engineer of record, from Wolf Water Resources, to create a scope of work and put the project out to bid in early 2025. Conditions of the scope will include a maximum road closure window of 9 days and that both construction options are addressed in the contractor's bid. The County will also meet with the Fire Marshall and Sheriff to ensure a robust emergency services plan is in place during road closure.

Project Brief

San Juan County is required by state law to replace a culvert located on Orcas Island under Killebrew Lake Road, just east of Laporte Road, with a fish-passable design. Funding for this project comes from FEMA and expires in early 2026. Replacement will occur in summer 2025.


Background

A storm in February of 2020 overwhelmed the culvert on Bayhead Creek under Killebrew Lake Road, just east of Laporte Road, and blew it out, causing catastrophic damage to the road and making it impassable. Following consultation from the Washington State Department of Fish and Wildlife (WDFW), San Juan County Public Works had the road reopened within 9 days after replacing the culvert with a temporary, 24-inch culvert under the condition the County would design a more permanent, fish-passable culvert. Now, with FEMA funding secured and a design in hand, the County is advancing plans to satisfy state requirements and install a 12-foot-wide box culvert specially designed to improve fish passage in Bayhead Creek and withstand future storms.


Construction Design

The County is considering several key factors in the construction design of this project, including cost, environmental impact, and how construction will affect the community. As such, two alternatives have been proposed - one that gets the job done as quickly and efficiently as possible but requires a maximum 9-day road closure, and a second that includes a single-lane bypass road for an estimated 3-4 weeks. These two designs are currently undergoing a constructability review with KBA, a construction management firm, to determine how each option will affect these variables. The County's goal is to minimize both inconvenience to the community and impact to the environment while staying within funding constraints.


Construction Window

This type of project typically requires dry weather to be completed efficiently. At the same time, the County wants to be mindful that the driest months of the year, July and August, are also our busiest in terms of traffic. As such, the County has identified two shoulder-season windows for starting construction: between Memorial Day Weekend and Fourth of July (if road closure option is chosen, road closure must be completed before Fourth of July), or after Labor Day Weekend. Physical construction will be completed within 45 days of the construction start date.


Next Steps & Timeline

After completion of the constructability review, the County will work with the engineer of record, from Wolf Water Resources, to create a scope of work and put the project out to bid in early 2025. Conditions of the scope will include a maximum road closure window of 9 days and that both construction options are addressed in the contractor's bid. The County will also meet with the Fire Marshall and Sheriff to ensure a robust emergency services plan is in place during road closure.

  • Community Meeting Reminder: Bayhead Creek Culvert Repair Project on Killebrew Lake Rd on Orcas Is.

    Share Community Meeting Reminder: Bayhead Creek Culvert Repair Project on Killebrew Lake Rd on Orcas Is. on Facebook Share Community Meeting Reminder: Bayhead Creek Culvert Repair Project on Killebrew Lake Rd on Orcas Is. on Twitter Share Community Meeting Reminder: Bayhead Creek Culvert Repair Project on Killebrew Lake Rd on Orcas Is. on Linkedin Email Community Meeting Reminder: Bayhead Creek Culvert Repair Project on Killebrew Lake Rd on Orcas Is. link
    supporting image

    SAN JUAN COUNTY, WA. January 6, 2025 – San Juan County is hosting a community meeting on Thursday, January 9, at the Orcas Landing to discuss the replacement of the culvert on Bayhead Creek under Killebrew Lake Road.

    Replacement of this culvert is required by state law, and San Juan County plans to begin construction in the 2025 summer shoulder season within a 45-day construction window and maximum 9-day road closure.

    At Thursday’s community meeting, San Juan County’s Department of Environmental Stewardship will give a brief presentation on the background and current status of the project before opening the floor for discussion to address additional community questions, comments, and concerns.

    Background

    A storm in February of 2020 overwhelmed the culvert on Bayhead Creek under Killebrew Lake Road, just east of Laporte Road, and blew it out, causing catastrophic damage to the road and making it impassable. Following consultation from the Washington State Department of Fish and Wildlife (WDFW), San Juan County Public Works had the road reopened within 9 days after replacing the culvert with a temporary, 24-inch culvert under the condition the County would design a more permanent, fish-passable culvert. Now, with FEMA funding secured and a design in hand, the County is advancing plans to satisfy state requirements and install a 12-foot-wide box culvert specially designed to improve fish passage in Bayhead Creek and withstand future storms.

    Please visit San Juan County’s Engage Page (https://engage.sanjuancountywa.gov/bayhead-killebrew-culvert) for more detailed information about this project.

    Contact: Tyler Davis, Project Manager Department of Environmental Stewardship, tylerd@sanjuancountywa.gov

    About San Juan County’s Department of Environmental Stewardship

    San Juan County’s Department of Environmental Stewardship is responsible for solid waste, marine resources, clean water, cultural resources, and climate and sustainability work. The department offices are located at 1609 Beaverton Valley Road, Friday Harbor, WA 98250. For more information about San Juan County’s Department of Environmental Stewardship, visit www.sanjuancountywa.gov/839/Environmental-Stewardship.

    ###