Construction Update: September 26

Progress on the Bayhead-Killebrew culvert replacement project continues on schedule, if a bit ahead of the anticipated October 17th completion date.

This week, crews focused on relocating utilities such as Opalco and water, and then placed riprap on the embankments for stabilization. They have also been prepping the road for resurfacing, which is planned for next week. Outstanding tasks include resurfacing, guardrail installation, and striping.